Aug. 19, 2025
Print | PDFThe Facilities and Asset Management department would like to inform the Laurier community of upcoming construction projects scheduled to take place on the Waterloo campus over the next few months.
Please review the details below, including expected impacts to campus areas.
FNCC/DAWB Chimney Demolition
Location: Exterior, FNCC and DAWB Buildings
Duration: August 25, 2025 through to December 2025
Scope of Work: Demolition of the chimney that is located between the FNCC and DAWB buildings
Expected Impacts: Outdoor construction noise, dust, vibrations related to construction activities
Arts C Roof Replacement
Location: Exterior, Arts C Building
Duration: August 21, 2025 through to November 2025
Scope of Work: Replacement of the low-sloped roof at Arts C
Expected Impacts:
Bricker Academic Building - Exterior Building Envelope Repairs
Location: Exterior, Bricker Academic Building
Duration: August 21, 2025 through to December 2025
Scope of Work: Restoration of deteriorated exterior building envelope components (brick masonry, EIFS, etc.)
Expected Impacts:
Thank you for your patience and understanding as we complete these important facility upgrades.